The short version: Florida HB 803, signed by Governor DeSantis on May 6, 2026 and effective July 1, 2026, lets single-family homeowners skip the building permit on most small projects worth less than $7,500. Five trades still need a permit no matter the cost — electrical, plumbing, structural, mechanical, and gas. Flood-hazard areas still need permits too. The same law also stops HOAs from demanding a permit before they will even review your improvement plan.

Quick answer — do you need a permit?

Skip the permit only if all four are true:

  1. The project costs less than $7,500 total (materials + labor)
  2. It does not involve electrical, plumbing, structural, mechanical (HVAC), or gas work
  3. Your home is a single-family dwelling (not a townhome, condo, or duplex)
  4. Your property is not in a flood-hazard area

Even if all four are true, you still owe the city a short written request, and the work must still meet the Florida Building Code.

< $7,500
Project value threshold — under this amount, a permit is not required for non-excluded work
July 1, 2026
Effective date per Section 12 of the enrolled bill
5 trades
Electrical, plumbing, structural, mechanical, gas — still permit-required regardless of value

Status Check — Yes, This Is Actually Law

Yes — HB 803 cleared both chambers unanimously and was signed into law. The full chronology:

DateAction
Feb 25, 2026House passes 114-0 (CS/CS/HB 803, sponsored by Reps. Trabulsy and Overdorf)
Mar 5, 2026Senate passes 37-0 (companion SB 1234 by Sen. DiCeglie laid on the table)
Mar 12, 2026House concurs 109-0 on Senate amendments — bill enrolled
May 6, 2026Signed by Governor DeSantis as Chapter 2026-63, Laws of Florida
July 1, 2026Effective date

The bill amends 11 sections of Florida Statutes — the headline change is the new permit-waiver provision at Fla. Stat. §553.79(1)(g). Other amended sections cover construction-bid procedures, contractor discipline, building inspector requirements, and the HOA architectural-review rule discussed later in this guide.

What the $7,500 Waiver Actually Says

The operative language is short. The new Fla. Stat. §553.79(1)(g)1 reads, verbatim:

Fla. Stat. §553.79(1)(g)1 — verbatim

"A local government that issues building permits shall exempt an owner of a single-family dwelling or the owner's contractor from the requirement to obtain a building permit to perform any work valued at less than $7,500 on the owner's property."

Three details about this language are worth pausing on:

"Shall exempt" — this is mandatory, not optional. A city or county that issues building permits cannot opt out, cannot require permits as a matter of local policy for projects under the threshold, and cannot impose alternative requirements that effectively reinstate the permit. The state-level rule overrides local choice.

"Less than $7,500" — the threshold is strict. A project valued at exactly $7,500 does NOT qualify; the exemption applies only to work valued at $7,499.99 and below. The bill does not index the threshold for inflation.

"Work valued at" — the value test is on the work itself, not on materials alone or labor alone. The written-request requirement (described later) requires submitting "a copy of the contract or other documentation demonstrating the nature and the value of the work to be performed," which strongly suggests the value is the total contract value including both materials and labor.

What Qualifies for the Waiver

The waiver does not give a list of eligible work types. It covers anything that is not on the exclusion list. In practice, these are the kinds of small home projects that typically stay clear of the five excluded trades and easily come in under $7,500:

To put real numbers on it: interior paint for a typical 1,800 sq ft Florida home runs roughly $2,500–$4,000. A standard fence replacement around an average lot runs $3,000–$6,000. A deck refinish runs $1,500–$4,000. All comfortably under the $7,500 cap. By contrast, a new HVAC condenser runs $5,000–$8,000 — even if the cost is below $7,500, it still needs a permit because it counts as "mechanical" work.

The list above is not exhaustive. Any project's eligibility depends on whether it touches one of the five excluded trades. A "simple deck repair" that includes running new outdoor lighting wiring is not eligible — the wiring is electrical work. A "cabinet replacement" that requires moving the plumbing for the sink is not eligible — moving the plumbing is plumbing work.

Selling or moving? Your biggest tax benefit is on the line.

Most Florida homeowners have tens of thousands of dollars in Save Our Homes protection — and lose it by accident when they move. Check what yours is worth and what happens to it if you sell.

Check My Save Our Homes Benefit

The Five Trades and Flood Areas Still Require Permits

Fla. Stat. §553.79(1)(g)2 carves two categories out of the exemption. Verbatim:

Fla. Stat. §553.79(1)(g)2 — exclusions, verbatim

"The exemption under subparagraph 1. does not apply to any of the following:

a. Work on a property that is partially or entirely located in a flood hazard area as defined by the Florida Building Code.

b. Any electrical, plumbing, structural, mechanical, or gas work performed on property containing a single-family dwelling. A construction project may not be divided into more than one project for the purpose of evading the requirements of this paragraph."

Infographic comparing what does and does not need a permit under Florida HB 803 effective July 1, 2026 for single-family homes only. Left column NO PERMIT NEEDED if project value is under $7,500: interior painting and drywall, exterior painting, cabinet and trim work, deck refinishing, fence repair and replacement, gutter replacement. Right column PERMIT STILL REQUIRED regardless of project value: electrical work, plumbing work, structural work, mechanical and HVAC work, gas work, anything in a flood hazard area. Warning bar: Anti-splitting rule means a $9,000 project cannot be divided into two $4,500 projects. Source: Fla. Stat. §553.79(1)(g), enacted by Chapter 2026-63 (CS/CS/HB 803).
When a permit is required vs. when it is not, under HB 803. Click to zoom.

The five excluded trades cover most of what would actually trigger a code review. New wiring or a new circuit. A new electrical panel. Adding or moving a plumbing fixture. Connecting to the sewer or water service. Removing or altering a load-bearing wall. Installing HVAC ductwork or a new condenser. Connecting a new gas line. All of those still need a permit regardless of cost. That's the substantial majority of projects that affect safety, code compliance, or insurance risk.

The flood-hazard-area exclusion is broad in coastal Florida. The Florida Building Code uses FEMA's flood maps to define a flood hazard area — typically the high-risk flood zones whose names start with "A" or "V" on your county flood map. Significant portions of Miami-Dade, Broward, Palm Beach, Pinellas, Lee, Collier, and Monroe Counties fall inside these zones. If your property is in one, the $7,500 waiver does not apply to your work. Pull up your county's flood map online and check your zone before assuming the waiver covers you. A homeowner on a barrier island, beachfront lot, or directly behind a tidal area almost always falls in the high-risk zone.

The anti-splitting clause is enforceable. The statute explicitly forbids dividing a single project into more than one project to stay below the threshold. A homeowner who splits a $9,000 deck rebuild into a $4,500 "framing" project and a $4,500 "decking" project does not qualify for the exemption, and a local enforcement agency that detects the split can require a permit and pursue other available remedies.

Single-Family Only — Condos and Townhomes Likely Out

The law specifically says "single-family dwelling." That phrase is narrower than it sounds in everyday speech. A separate part of the same bill — the hurricane and flood barrier exemption — uses a broader phrase: "single-family or two-family dwelling or townhouse." Because the legislature chose the narrower phrase for the $7,500 waiver, the waiver almost certainly does not extend to:

Owners of those property types should confirm with their local building department whether any local-option extension of the waiver is available, but the safer default is to assume the $7,500 waiver applies only to detached single-family dwellings.

The Paperwork You Still Owe the City

"No permit" does not mean "no paperwork." Fla. Stat. §553.79(1)(g)3 requires that, to qualify for the exemption, the owner or owner's contractor must:

Fla. Stat. §553.79(1)(g)3 — written request, verbatim

"To qualify for the exemption under subparagraph 1., the owner or the owner's contractor must submit a written request for exemption to the local enforcement agency with a copy of the contract or other documentation demonstrating the nature and the value of the work to be performed."

The mechanics are simple: send the city or county a brief written request stating that the project qualifies, attach a copy of the contract or a written description of the work that shows its value is under $7,500, and keep a copy of what you sent. Many local building departments are expected to publish a simple online form by July 1.

Subparagraph 4 then adds an important consequence:

Fla. Stat. §553.79(1)(g)4 — "no legal duty," verbatim

"A local government has no legal duty to the owner, contractor, or successors or assigns thereof for exempted work performed under this paragraph."

"Successors or assigns" means anyone who later owns the home or anyone you transfer your interest to — future buyers, heirs, and so on. So in plain English: the city is not standing behind this work, for you or for anyone who comes after you. The state waived the permit. It also told local governments they bear no liability for what happens next. That makes choosing a good contractor, meeting the building code, and keeping good records more important, not less.

HB 803 Also Stops HOAs From Demanding a Permit First

One of the most consequential pieces of HB 803 is not in the permit section at all — it is in the homeowners' association statute. Section 11 of the bill adds a new paragraph to Fla. Stat. §720.3035 (architectural control covenants), which reads verbatim:

Fla. Stat. §720.3035(1)(c) — HOA permit prerequisite ban, verbatim

"An association or any architectural, construction improvement, or other such similar committee of an association may not require a building permit to be issued by a governmental authority to a parcel owner as a prerequisite for review by the association or committee concerning the construction of structures or improvements on the parcel."

Infographic showing how Florida HOA architectural review changes on July 1, 2026 under HB 803 amending Fla. Stat. §720.3035(1)(c). Before column (until June 30, 2026): Step 1 owner submits improvement plan to HOA; Step 2 HOA refuses to review until owner produces a building permit; Step 3 owner pays permit fees and design costs upfront; Step 4 HOA may then reject the plan anyway, owner is out the money. After column (July 1, 2026 onward under HB 803): Step 1 owner submits improvement plan to HOA; Step 2 HOA must review on the merits, no permit prerequisite allowed; Step 3 HOA approves, denies, or conditions on aesthetic standards; Step 4 owner pursues permit only if and when needed. Bottom note: HOAs can still apply their own architectural standards, they just cannot gatekeep behind a city permit.
The HOA permit-first delay tactic, before and after HB 803. Click to zoom.

For the millions of Florida homeowners living in HOA-governed communities, this is a substantial change. A common HOA practice has been to demand that an owner obtain a building permit before the architectural review committee will even look at the application — effectively forcing the owner to incur permit fees and design costs for a project the HOA might then reject on aesthetic grounds. As of July 1, 2026, that practice is unlawful. The association can still require its own architectural review, can still apply its own aesthetic standards, and can still ultimately deny or condition approval. What it can no longer do is gatekeep that review behind a city-issued permit.

This provision pairs sensibly with the $7,500 waiver itself: if the work no longer requires a permit at the city level, demanding one as a precondition for HOA review would have functionally killed the legislative purpose. The HOA provision closes that loophole.

No Permit Does Not Mean No Florida Building Code

This is the single most misunderstood point about HB 803, and it is worth stating directly: the work still has to meet the Florida Building Code. A permit waiver is a procedural waiver — it removes the requirement to file an application, pay fees, and undergo a pre- and post-work inspection. It does not relax the substantive standards the work must meet.

For a coastal or hurricane-prone state, those substantive standards matter:

If a future inspection (triggered by a complaint, a buyer's inspection, or a later permit on related work) determines that exempt work was not code-compliant, the homeowner is responsible for bringing it into compliance — and may bear the cost of any related damage.

Your Contractor Still Needs to Be Licensed

HB 803 does not change Florida's contractor-licensing rules. A contractor performing any of the five excluded trades (electrical, plumbing, structural, mechanical, or gas) still needs the proper state or local license for that trade. The waiver doesn't authorize unlicensed work.

For the work that qualifies for the waiver, Florida's licensing rules already have several built-in exemptions for general handyman-type tasks — but those exemptions have their own conditions. The safest practice is to ask any contractor for proof of license before they start, even when a permit is not required. A licensed contractor's liability insurance is also what backstops any damage they cause to your home.

Doing the work yourself? Florida lets a homeowner do certain work on their own home without a contractor's license, but with conditions: you have to live in the home for at least a year after the work, and you cannot sell or rent it during that year. If you might sell sooner, hire a licensed contractor instead.

Insurance and Resale — Still Risks Worth Managing

Two practical concerns survive HB 803 and deserve attention before any homeowner takes advantage of the waiver:

Insurance. If exempt work fails or causes damage, the homeowner's insurer may decline coverage under the policy's exclusions for damage caused by the insured's own work or by code violations. Florida insurers have shown willingness to deny claims where the underlying repair was not performed to code, even where no permit was required. Protections: hire licensed contractors, keep documentation showing the work meets the Florida Building Code, and consider asking the insurer about the implications before starting a non-trivial project.

Resale. Florida's seller-disclosure rule (under the well-known Johnson v. Davis case) requires you to tell a buyer about anything that materially affects the home's value and is not obvious to them just by looking. Work done under HB 803 is permit-free under state law, but a careful buyer's agent or inspector will still ask whether work was done and whether there are records. Keep the written exemption request you sent the city, the contractor's invoice and contract, photos of the work, and any voluntary inspection records. Title companies and lenders generally check for "open permits" only — HB 803 work will show no open permits, which is the result you want — but your records are what protects you if a buyer or future inspector asks questions.

Practical Checklist Before Starting a Project

Steps to take in order, starting before you order any materials:

Frequently Asked Questions

Common questions Florida homeowners ask about HB 803 and the new $7,500 permit waiver, answered with the underlying statute or enrolled bill text cited.

July 1, 2026. The waiver was enacted by CS/CS/HB 803 of the 2026 Regular Session, signed by Governor DeSantis on May 6, 2026, and became Chapter 2026-63, Laws of Florida. Until July 1, the existing permit rules apply; do not act on the waiver before then.

Starting July 1, 2026, any work on a single-family dwelling valued at less than $7,500 — except for work in flood hazard areas and except for any electrical, plumbing, structural, mechanical, or gas work. Examples of work that typically does NOT involve those five trades include interior painting, drywall repair, exterior painting, cabinet replacement, trim and molding, deck refinishing, fence repair, screen-porch repair, gutter replacement, and most simple sheds. The exact treatment of any specific project depends on whether it touches one of the five excluded trades.

Five trades are explicitly carved out of the exemption regardless of project value: electrical, plumbing, structural, mechanical, and gas work performed on property containing a single-family dwelling. In addition, any work on a property partially or entirely in a flood hazard area as defined by the Florida Building Code still requires a permit. So replacing an HVAC unit, rewiring an outlet circuit, repairing a sewer line, replacing a load-bearing wall, or installing a gas appliance line all still require a permit even if the cost is below $7,500.

No. The enrolled bill includes an explicit anti-splitting clause at Fla. Stat. §553.79(1)(g)2.b: "A construction project may not be divided into more than one project for the purpose of evading the requirements of this paragraph." A local enforcement agency that detects splitting can require a permit and pursue any other available remedies.

The $7,500 waiver applies only to "an owner of a single-family dwelling." A separate hurricane/flood barrier exemption in the same bill (§553.79(1)(h)) lists "single-family or two-family dwelling or townhouse" explicitly, which suggests the headline $7,500 waiver is narrower and does not automatically cover townhomes, two-family duplexes, condos, or multi-family. Owners of those property types should confirm with their local building department before relying on the waiver.

Yes — and this is the under-discussed half of the bill. HB 803 amends Fla. Stat. §720.3035 to prohibit an HOA (or its architectural/improvement committee) from requiring a building permit be issued by a governmental authority as a prerequisite for the association's own review of a parcel owner's proposed improvements. The text reads: "An association or any architectural, construction improvement, or other such similar committee of an association may not require a building permit to be issued by a governmental authority to a parcel owner as a prerequisite for review by the association or committee concerning the construction of structures or improvements on the parcel." Effective July 1, 2026, that delay tactic is no longer permitted under state law.

Possibly not. A permit waiver under HB 803 is a permit waiver, not a Florida Building Code waiver — the work must still comply with the Florida Building Code, including hurricane wind-resistance and coastal requirements. If the work is later found to be non-compliant or to have caused damage, the insurer may deny a claim, particularly under the policy's exclusion for damage caused by the insured's own work or by code violations. The smart approach is to (a) keep your contractor licensed under Chapter 489, (b) keep documentation showing the work meets the applicable code, and (c) check with your insurance carrier before starting anything significant.

Florida real estate law requires sellers to disclose material facts that materially affect the value of the property and are not readily observable to the buyer (the Johnson v. Davis duty). Work performed under the HB 803 waiver is permit-free under state law, but a careful buyer will still ask. Keeping your contractor's documentation, your written request for exemption, and any inspection or certification records makes the resale conversation much easier and reduces the risk of disclosure disputes.

Selling or moving? Your biggest tax benefit is on the line.

Most Florida homeowners have tens of thousands of dollars in Save Our Homes protection — and lose it by accident when they move. Check what yours is worth and what happens to it if you sell.

Check My Save Our Homes Benefit

Share this guide